Work Package 1: Overall project coordination | ||||
Deliverable Number | Deliverable Title | Type | Dissemination level | Due Date (month) |
D1.1 | Project_handbook (*) | Report | Confidential | 2 |
D1.2 | Data Management Plan and Quality Management Plan (*) | ORDP | Confidential | 4 |
D1.3 | Project Management Collaborative Space (*) | Other | Confidential | 4 |
D1.4 | 1st Technical Report to EC | Report | Confidential | 12 |
D1.5 | 2nd Technical Report to EC | Report | Confidential | 24 |
D1.6 | 3rd Technical Report to EC | Report | Confidential | 36 |
ORDP: Open Research Data Pilot
(*) abstract available
Work Package 2: Definition of materials requirements | ||||
Deliverable Number | Deliverable Title | Type | Dissemination level | Due Date (month) |
D2.1 | Preliminary selection of materials compositions and TES system predesign | Report | Public | 4 |
D2.2 | Key performance indicators (*) | Report | Confidential | 5 |
D2.3 | Specific scenarios (*) | Report | Confidential | 5 |
(*) abstract available
Work Package 3 – Validation, cost & benefits analysis and dissemination | ||||
Deliverable Number | Deliverable Title | Type | Dissemination level | Due Date (month) |
D3.1 | Intermediate Report on Ternary mixtures (*) | Report | Confidential | 10 |
D3.2 | Material development progress report (*) | Report | Confidential | 12 |
D3.3 | Report on thermal properties of filler rock material for sensible heat storage (*) | Report | Confidential | 16 |
D3.4 | Report on new CAC-based concrete with enhanced thermal resistance (*) | Report | Confidential | 18 |
D3.5 | Report on new Ca-ternary mixtures and nanoparticles (*) | Report | Confidential | 18 |
D3.6 | Thermal behaviour of new encapsulated PCMs (*) | Report | Confidential | 18 |
D3.7 | New insulating materials solutions (*) | Report | Confidential | 19 |
D3.8 | Report on Lithium mixtures (*) | Report | Confidential | 20 |
(*) abstract available
Work Package 4 – Advanced materials combination and stability | ||||
Deliverable Number | Deliverable Title | Type | Dissemination level | Due Date (month) |
D4.1 | Interaction characteristics of sensible-heat storage materials combinations (*) | Other | Confidential | 18 |
D4.2 | Compatibility of metallic materials with PCMs and sensible-heat Ca-ternary salts (*) | Report | Confidential | 20 |
D4.3 | Concrete long-term performance model (*) | Report | Confidential | 20 |
(*) abstract available
Work Package 5 – System Architecture design: simulation and materials monitoring | ||||
Deliverable Number | Deliverable Title | Type | Dissemination level | Due Date (month) |
D5.1 | System configuration for thermocline concrete tank (*) | Report | Confidential | 25 |
D5.2 | System configuration for concrete module (*) | Report | Confidential | 23 |
D5.3 | Sensor monitoring design (*) | Report | Confidential | 25 |
D5.4 | Lab scale monitoring system (*) | Report | Confidential | 25 |
D5.5 | Thermocline and module TES designs and drawings (*) | Report | Confidential | 25 |
(*) abstract available
Work Package 6 – System integration and demonstration | ||||
Deliverable Number | Deliverable Title | Type | Dissemination level | Due Date (month) |
D6.1 | Quality in-situ control report (*) | Report | Confidential | 28 |
D6.2 | Test operation of the thermocline concrete tank and the modular concrete | Report | Confidential | 36 |
D6.3 | Data evaluation after demo phase | Report | Confidential | 37 |
(*) abstract available
Work Package 7 – Validation, cost & benefits analysis and dissemination | ||||
Deliverable Number | Deliverable Title | Type | Dissemination level | Due Date (month) |
D7.1 | Project visual identity and web-site | Other | Public | 4 |
D7.2 | Dissemination plan (*) | Report | Confidential | 5 |
D7.3 | Mid-term report on dissemination activities | Report | Public | 21 |
D7.4 | KPIs updated | Report | Confidential | 36 |
D7.5 | Techno-economical assessment of the new thermal energy storage concepts | Report | Confidential | 38 |
D7.6 | Summary report on validation activities | Report | Confidential | 40 |
D7.7 | Final report on dissemination activities | Report | Public | 42 |
(*) abstract availablehttp://www.newsol.uevora.pt/_newsol/wp-content/uploads/2021/04/V1_D8_1_Exploitation-Plan-Intermediate-Materials.pdf
Work Package 8 – Exploitation of results and Bankability of applied materials solutions and system architectures | ||||
Deliverable Number | Deliverable Title | Type | Dissemination level | Due Date (month) |
D8.1 | Exploitation Plan Intermediate – Materials (*) | Report | Confidential | 26 |
D8.2 | Guidelines for materials processing and operation | Report | Confidential | 38 |
D8.3 | Exploitation plan | Report | Confidential | 40 |
D8.4 | NewSOL bankability report | Report | Confidential | 40 |
D8.5 | One-year get-to-the-market roadmap | Report | Confidential | 42 |
Work Package 9 – Ethics requiements | ||||
Deliverable Number | Deliverable Title | Type | Dissemination level | Due Date (month) |
D9.1 | NEC – Requirement No. 1 (*) | Ethics | Confidential | 3 |
D9.2 | EPQ – Requirement No. 2 (*) | Ethics | Confidential | 5 |
(*) abstract available